How long does a custom machine take to build?

By I&R Group, Jiaxing. Reviewed October 3, 2026.

A standard machine runs about 25 to 45 working days; a customized machine or a complete line is usually 45 to 60 or more, because of tooling, special components and the factory acceptance test. Add sea freight of roughly three to seven weeks and customs clearance. Lock the specification early, since late changes reset the production clock.

  • Standard: 25–45 working days; custom: 45–60+ working days.
  • Then sea freight (about 3–7 weeks) and clearance.
  • Freeze the spec early; changes mid-build push the date out.